"Nothing Will Be Lost" Is a Promise. A Benchmark Is Something You Can Check.

No technology head can honestly promise a new system does everything the old one did. Here is the benchmark we would set before go-live, and how it is checked function by function.

By 9 min read Figures checked against their sources on October 11, 2026

You are in the steering committee for the new lending system. Go-live is six weeks away.

The chief executive asks one question. Can you promise that everything the old system does today, the new one will do on day one?

You look at the test report. Every test has passed. You also know what the tests were written from: a requirements document, which was written from interviews, which captured what people remembered.

The paradox: You are asked to promise that the new system matches the old one, and nobody can tell you what the old one does.

What We Found

We looked at where the rules of an old lending system are kept, and at what the public record says about the moment a replacement goes live.

The rules are in the code. A special rate for one customer group. A waiver agreed in a meeting. A rounding rule added after an audit. Each one was a small change at the time. None of them reached a document.

Some rules are not in the application at all. They sit in the database as stored procedures (small programs that run inside the database). They sit in scheduled jobs that run overnight. They sit in a spreadsheet someone in finance uses to correct a figure every month end.

The scale is beyond memory. When one group of more than 40 credit unions replaced a core system, the work meant rebuilding more than 200 screens and more than 500 interfaces to other systems. No round of interviews brings all of that out.

Going live is when every gap shows at once. When TSB Bank went live on its new platform in 2018, the bank received 225,492 complaints and was later fined £48.65 million.

What our review does not show: The first two findings are our own reasoning about how old systems grow. The record does not say why TSB’s migration failed in terms of testing, and we do not claim it. Both named cases are from outside India, and one is a large bank.

What a Proved Replacement Opens Up

Proof of a match is usually seen as protection: against complaints, corrections and questions from the auditor. It is that. Our reading is that it is also an asset the business did not have before.

  • A system that is written down can be changed with confidence. The next product variant or fee change starts from a record of what the rule is today.
  • Figures can be explained. When a customer or the finance team asks why a number is what it is, there is a written rule to point to.
  • The record is ready when someone asks. One 2025 survey of 500 leaders at large enterprises reported that 94% said regulatory compliance strongly influences their modernisation decisions.

The gap we see: most lenders running an old system cannot state, in writing, what it does. A lender that can has something the others lack. The replacement is the moment to get there, because the work of proving a match produces the record.

This is our reading. It is not a measured market figure.

Three Ways to Decide You Are Ready, Weighed

OptionWhen it fitsWhat it risks
Test the new system against the requirements documentThe old system was fully documented and the document was kept up to dateThe tests are incomplete in exactly the places the document is. Missing rules fail silently
Run the whole old and new systems side by side, then switchThe system is small enough to compare as a wholeDifferences are found late and all at once, close to the switch
Check each function against a written record, one module at a timeThe system is old, customised and poorly documentedWriting the record takes time before any new code is written

Our recommendation: for an old, customised system, check function by function, one module at a time. The question changes from “are we confident?” to one that can be answered with a document: for each thing the old system does, where is it in the new system, and how was it checked?

Where You Are Now, and Where You Should Be

This is the benchmark we would set before the first module is built, and fill in as each module is accepted.

MeasureTypical starting pointWhere it should beHow it is checked
Functions with a written lineA requirements document written from interviewsEvery rule, report, calculation and interface in the module has its own numbered lineThe record is compared with the code, the database and the scheduled jobs
Functions linked to their replacementNo link is keptEvery line points to the place in the new system that does the same thingThe traceability matrix
Functions compared, old against newTests run against the documentThe same input is given to old and new, and the results are comparedThe result is recorded on each line
Where gaps are foundBy customers or finance, weeks after go-liveDuring the check, before the module goes liveThe record of gaps found and fixed
Who accepts each moduleOne sign-off for the whole systemA named person signs each module, with the table in front of themSigned acceptance for each module
Rules nobody can explainCarried across unseen, or dropped unseenEach one listed, for the business to decide what to keepThe decision is recorded on its line

The starting points above are what we expect to find. In an engagement they are replaced by your own position, taken in the first review. The targets are what we would work towards with you. They are not results we have already achieved for a lender.

A small part of the finished record might look like this.

Old systemNew systemHow it was checkedResult
Penal interest on overdue instalments, rule 14Interest module, overdue calculation200 sample accounts run through bothMatch
Monthly report to finance on written-off accountsReporting module, report 7Last three month ends comparedMatch
Overnight file of repayments sent to the collections agencyIntegration module, job 3Seven nights of files comparedOne field differs: fixed and re-run

The rows above are an illustration, not taken from a real system.

How We Work With You, and What You Are Left With

  1. We listen: a free Reliability Review. A first conversation about the system, the go-live decision, and who is being asked to make the promise. You leave with a short written note of what we found.
  2. We research. We research your sector, the regulator’s position and what the public record says about firms in your situation.
  3. We read the system and propose: the Legacy System Specification Assessment. It produces a written specification of what the system does. AI does a first pass, our senior engineers review it and trace it to the code, and your own experts confirm it. You can start with a conversation about the system; we ask for read-only code access only when the assessment begins. Code access is read-only and logged, never used for training, and deleted within 30 days of the evaluation ending unless we engage.
  4. If you approve, we build. We replace a system one module at a time while the old one keeps running. We never do a single cutover. A traceability matrix links every old function to its replacement. The work is billed by milestone, each milestone tied to a module you accept, and you can pause after any accepted module.
  5. We review against the benchmark. Before work starts we set the benchmark above. As each module is accepted we show you where each measure stands, and the filled-in benchmark is yours at the end.

The Review is free. Every paid step is fixed price, agreed at scoping. Stop after any step. The findings are yours. The assessment fee is credited in full against the first build stage if it starts within 90 days of the report.

This has a price. Writing the record takes time before any new code is written. It will also turn up rules that nobody can explain, and some will be mistakes the old system has been making for years. The business then decides, rule by rule, what to keep. That is slower than not knowing. It is also the first time anyone has decided.

At the end you hold three things: the specification, the matrix, and the benchmark with every line filled in.

What changes for the business:

RoleWhat they gain
CEOA go-live decision made on evidence.
CTO or CIOA documented system, which makes every later change quicker and safer.
CFOFigures that can be explained from the first month end.
COOStaff start on a system that behaves as they expect.
Risk and complianceA record for every function, ready for audit.

The cases in this article, and what IOanyT does about that kind of problem:

The caseWhat IOanyT does
TSB Bank received 225,492 complaints when its new platform went live.We check each module against a written record of the old system, with a traceability matrix, before that module goes live. Gaps are found by us, not by customers.

IOanyT is a consultancy with its own engineering team: we study the problem, recommend, and prove it by building only what you approve. The next time someone asks whether anything will be lost, you hand them the table.